Mitchell Fwy Southbound Widening (Vincent st to Cedric st)

BMD

Osborne Park, WA

Scope of Work

  • 8101 Lm TL5 Concrete Slipform Barrier
  • 1152 Lm TL4 Concrete Slipform Barrier

Highlights

There was a constructability challenge throughout the project where the slipform machine had to slip over the designed drainage blockouts and had difficulty preventing the blockout from moving. We proposed to fix the blockout to the concrete embedment to prevent moving.

Timeline

April 2019 – May 2020

9253
Lineal Metres
5244
m3 of Concrete
8527
Project Man hours