Kwinana Fwy Northbound Widening (Between Farrington Rd & Narrows Bridge)
Smartways Alliance
South Perth, Como
Scope of Work
Dowsing was awarded the slipform barrier contract by the Smartways Alliance in October 2019.
- 4550m of TL5 Slipform Barrier with 75mm – 200mm embedment
Highlights
95% of the project was completed within night shift hours next to live traffic. The mould modifications allowed us to be able to slipform over the top of a cold joint concrete footing with dowels placed every 500mm apart.
800m of barrier was also completed adjacent to an atco drain with a 5mm alignment tolerance.
Timeline
Oct 2019 – May 2020






4550
Lineal Metres
3110
m3 of Concrete
1996