Armadale Rd Upgrade & Murdoch Drive Connection
Metropolitan Road Improvement Alliance
Piara Waters & Bibra Lake, WA
Scope of Work
Dowsing’s scope was a full supply and installation of permanent Slipform Barriers in accordance to MRIA specifications.
- 4400Lm of TL4 Slipform Barrier
- 4100Lm of TL5 Slipform Barrier
Highlights
Dowsing had capacity to be able to run 2 x separate Slipform crews concurrently across both projects when required.
Timeline
July 19 – Feb 20








8500
Lineal Metres
4200
m3 of Concrete
6357