Mitchell Fwy Southbound Widening

Fulton Hogan

Osborne Park, WA

Scope of Work

Profiling existing asphalt surface in preparation for Fwy asphalt overlay.

  • Approximately 60,000 m2 @ varying depths from 0 – 40mm

Highlights

This job was successfully completed over consecutive night shifts.

Timeline

Jan 2020 – March 2020

60000
m2 Profiled
452
Man hours