The scope involved profiling the road surface at 1m width and 150mm depth, followed by placement of MRWAapproved quarry and borrow pit material processed through an onsite pugmill and re-laid by side paver — all executed within lane closures on a live regional highway.
Profiled material was unsuitable for reuse and was removed from site. Replacement material was sourced from MRWA approved quarries and borrow pits, conditioned to the required optimum moisture content through the onsite pugmill, then placed by side paver. The team achieved up to 3-4km and 1,200 tonne per shift, operating within a 1.6km working room created by lane closure tapers.
Client
Sector
Project Type
Location
Duration
Type
Scope of works included:
- 1m wide profiling at 150mm depth under live lane closures
- Works conducted under 2km lane closures with 1.6km effective working room
- Initial sections side cast; MRWA-supplied 8-wheel trucks
deployed for haulage as works progressed - MRWA-approved quarry and borrow pit material processed through onsite pugmill to achieve 8.5% optimum moisture content
- Material placed by side paver at 1m width
- Production rate of up to 3-4km and 1,200 tonne per shift
With Dowsing’s in-house plant, equipment, and experienced crews deployable across metropolitan and regional WA, we self-perform complex civil and road works without reliance on external resourcing.
Projects like Brand Highway reflect our ability to mobilise quickly, manage multi-faceted operations in remote environments, and maintain production rates that meet client expectations.