Railway Parade PSP

City of Armadale

Railway Parade Kelmscott WA

Scope of Work

The scope of works comprised the constructing of a 600m long principle shared path split into 2 sections.

  • Box out of material and disposal
  • Import of road base, place compact and trim
  • Supply and lay 600m Long x 4m wide 30mm red laterite asphalt
  • 4 x pram ramps
  • Traffic management
  • Misc concrete island infill

Highlights

All works were completed at night within a 3 week period. Section 1 involved liaison with the local train station. Section 2 involved a train line closure to have the works completed. Due to the nature of the work, a complex traffic management plan was implement on a nightly basis with several detours put in place.

Timeline

Sep 2019

600
Lineal Metres
180
Tonnes of Asphalt
282
Project Man hours