Northlink WA 2

Great Northern Connect Alliance

Malaga, WA

Scope of Work

GNC selected Dowsing Group to deliver the entire concrete footpath and concrete infill scope below:

  • Supply and install 7662m2 of 2.5m & 4m Concrete Footpaths
  • Supply and install 2628m2 of concrete infill

Highlights

Dowsing was able to consistently pour 80m3 > per shift whilst continually liaising with other sub-contractors on site.

Timeline

Sep 2018 – March 2019

1168
m3 of Concrete
10290
m2 Total Area
2896
Project Man hours