NorthLink 2

Great Northern Connect

Malaga, WA

Scope of Work

Kerb & Island Backfill

  • Conditioning of laterite material
  • Placement laterite behind all kerbing and island infill to a depth of 150mm
  • Placement of laterite flush with road level for W-beam & wire rope base preparation
  • All placed laterite was compacted and trimmed to Main Roads tolerances and specification

Highlights

We had to adapt our machine and methodology to allow placement of laterite material behind kerb which had never been done before.

Timeline

Nov 2018 – Apr 2019

19945
Lineal Metres
15819
m2 of laterite placed
6819
Project Man hours