Bus Embayment Brookton Hwy

Public Transport Authority

Brookton Hwy Roleystone, WA

Scope of Work

  • Embankment construction
  • Box out to disposal
  • Concrete driveway removal
  • Import of sub-base material, placement, compaction & final trim
  • Import of base course material, placement, compaction & final trim
  • Installation of primer seal
  • Installation of semi-mountable kerb, mountable kerb & barrier kerb
  • Concrete driveway reinstatement
  • Installation of concrete bus hardstand and pram ramp
  • Kerb backfill
  • Installation of dense grade asphalt
  • Linemarking
  • Installation of native planting on embankment construction
  • Installation of fencing at back of bus hardstand
  • Traffic management

Highlights

Delivered to Main Roads specification on time with minimal disruption to local residents.

Timeline

Apr 2019 – May 2019

6
week program
502
Project Man hours